WATER USAGE AND WATER
PRESSURE INFO
From: Richard Adams [mailto:radams@ci.palm-coast.fl.us]
Sent:
To: Paul Zacharias
Subject: Watering
restrictions
Dear Mr. Zacharias,
Thank
you for your efforts to conserve water by adhering to the
The Water Management District is currently in the process of adopting new rules that will most likely limit irrigation to two days per week. In most cases, turf grasses do fine on one thorough watering per week, about ¾” to 1”. During extreme dry conditions with well drained soils, it could be necessary to water twice per week to maintain lush foliage; however, the grass will survive the dry period with less. It is a matter of “training” the grass to develop deep roots with periods of wet and dry conditions.
Again thank you and your neighbors for doing your part to conserve this precious resource. If I can be of further help please do not hesitate to contact me.
Richard Adams
Utility Director
Also see http://sjr.state.fl.us/govboard/index.html
where the proposal to be voted on
The current districtwide rule allows lawn and landscape irrigation
only before
-----Original Message-----
From: Richard Adams [mailto:radams@ci.palm-coast.fl.us]
Sent:
To: Dennis Clark
Subject: RE:
Plans to correct low water pressure?
Dear Mr. Clark,
During
peak flow periods we continue to experience low water pressure in the extreme
north east section of our water distribution system. This is most severe
during the early morning hours when irrigation demand increases. Flow
rates on the north end of the Hammock and in the canal area of
First
and foremost is a new 16” water main along State Road 100 that will run from
Currently
under construction is a 12” water main along
We
also have entered into a Joint Project Agreement with
In addition, we have issued a $ 500,000 contract to construct booster pumps and valve controls at our elevated tanks. Equipment is on order and will be installed upon delivery, we’re estimating about two months. This system improvement will better enable us to fill the storage tanks during off peak periods and regulate flow from the tanks during peak flow periods.
Other
projects to improve systems pressures are in the design phase, the largest one
being our proposed Water Treatment Plant Number 3. It is estimated that
this project will cost nearly $20 million with a completion time projected by
mid 2007. Part of this project will be the completion of a large water
main from the new plant to the new
While I realize none of these improvements provide immediate relief, we are working as diligently as we can to complete them as soon as possible.
I hope this email has provided you with the information you need to properly address your association. Should you have additional questions, please do not hesitate to contact me.
Sincerely,
Richard Adams
Utility Director